Steam Early Access -> Full Release Transition Guide

IkesanContents

The steps for moving from Early Access to a full release. Unlike the initial launch, there is no review, and there is much less to do.

Transition Steps

1. Remove the Early Access Flag

Unset Early Access in the “Store Presence” -> “Early Access” section.

2. Change the Price if Needed

If you want to change the price for the full release, submit it through “Pricing & Discounting.”

Notes:

  • After changing the price, you cannot change it again for 30 days
  • Approval may take time, so submit it with some buffer
  • Existing buyers are unaffected and do not need to buy it again
  • For a large price increase, advance notice to the community is recommended

3. Update the Build if Needed

If you want to ship a new build as the full-release version:

  1. Upload the new build with SteamPipe
  2. Do not set it as the default branch yet (if you do, it will go live immediately)

If you want to use the existing build as the full release, this step is unnecessary.

4. Publish

Once all changes are ready, press the “Publish” button to finish.

5. Set the Branch to default

After publishing, set the new build to the default branch. The order matters.

Unlike the initial release, build updates do not go through review. The moment you set the default branch, the update starts distributing to users.

Differences from the Initial Release

ItemInitial releaseTransition to full release
ReviewYes (a few days)No
FAQ answersRequiredNot required
ChecklistMany itemsAlmost none
Time requiredDaysImmediate

If you remember how painful the initial launch checklist and FAQ were, this transition may feel almost suspiciously easy.